Deutz 914 Technical Information Seite 27

  • Herunterladen
  • Zu meinen Handbüchern hinzufügen
  • Drucken
  • Seite
    / 85
  • Inhaltsverzeichnis
  • LESEZEICHEN
  • Bewertet. / 5. Basierend auf Kundenbewertungen
Seitenansicht 26
3
© 2001
Checking battery and cable connectors
see 6.7.1
Transport hooks
Remove if fitted (see 6.7.3)
Trial run
After the engine has been prepared, let it run
for about 10 minutes without load.
During and after trial run
Check the engine for leaks.
After the engine has been turned off
Check the oil level, see 6.1.2
If necessary, top up oil, see 3.1.1
Retension V-belts, see 6.5.
Breaking in
During the break-in phase, about 200 oper-
ating hours, check the oil level twice a day.
After the engine is broken in, checking once
a day will be sufficient.
3.1.6 Additional maintenance
work
Engine Operation 3.1 Commissioning
After 50-150 operating hours, the following
maintenance work is to be carried out:
Change lube oil,
see 6.1.2
Change oil filter cartridge,
see 6.1.3
Change fuel filter cartridge,
see 6.2.1
lCheck V-belts and retension as necessary,
see 6.5.
Check valve clearance (adjust if neces-
sary) see 6.6.1
Check the engine for leaks
Check engine mounts (retighten if neces-
sary) see 9.2.
3.1.5 Other Preparations
3.1.7 Change-over switch for oil
heater
Position of change-over switch for oil filter
consoles with an oil heater connected:
Pos. 1: open
Pos. 2: closed
For engines without an oil
heater, the change-over switch
should
always be fixed to Pos.
2: closed.
© 30 027 0
Seitenansicht 26
1 2 ... 22 23 24 25 26 27 28 29 30 31 32 ... 84 85

Kommentare zu diesen Handbüchern

Keine Kommentare